Difference between revisions of "Not Possible to Unapprove"

From IMSMA Wiki
Jump to: navigation, search
Line 1: Line 1:
 +
{{Warning| The Unapprove feature should '''NOT''' be used to correct or delete data because if you use Unapprove Action then all traceability and transparency are lost.
 +
If you need to correct data, you should create a new Data Entry Form using the '''[[Update from Summary Window | Update]]''' action.
 +
 +
If you need to delete an item, you should create a new Data Entry Form using the '''[[Delete from the Summary Window | Delete]]''' action.
 +
}}
 +
 +
[[Image:Inactive Unapprove.png|300px|center]]
 +
<div align="center">
 +
'' Inactive vs Active button''
 +
</div>
 +
When the [[Unapprove a Data Entry Form from the Summary Window| Unapprove]] button is inactivated then it is not possible to Unapprove that Data Entry Form.
 
The most common reasons why it is not possible to Unapprove are:
 
The most common reasons why it is not possible to Unapprove are:
* there are other items linked to the item (approved or in the workbench)
+
* there are other items linked to the item
* something is wrong in the Link table
+
: The other items may be approved or in the workbench
* trying to Unapprove a DEF that is not the last one in an updating chain
+
 
* the DEF is linked to another DEF but Date of Information are not chronological.
+
 
Example 1 (Albania)
+
* there are other Data Entry Forms that are updating the item with later dates i.e. is not the last one in an updating chain
: Victim-1 has Date of Information 2013-11-23.  
+
: Example 1: an Accident was created and approved with ''Date of Information'' '''2014-02-14'''.  
: Victim-2 with Date of Information 2013-10-29 is linked to Victim-1.
+
: Later the Accident is updated with ''Date of Information'' '''2014-02-20''' and with a third Data Entry Form which has ''Date of Information'' '''2014-05-05'''.  
: User is trying to Unapprove Victim-2 but is getting error message because Victim-1 is newer than Victim-2 based on Date of Information.
+
: It is not possible to Unapprove the Data Entry Form with '''2014-02-20''' due to it exists Data Entry Forms with newer Date of Information.
: The reality was that Victim-1 should had Date of Information 2012-09-23. After correction by SQL of Victim-1's Date of Information it was possible to Unapprove Victim-2.
+
 
  
Example 2 (Ecuador)
+
* the Data Entry Form is linked to another Data Entry Form but Date of Information are not chronological.
QM is linked to Land. Land has Date Of Information 2003-11-27 and QM 2000-02-28 then Unapproving the QM will not work.
+
: Example 2: a Land was created and approved first with ''Date Of Information'' '''2003-11-27'''.
 +
: Later a QM was created and approved with link to the Land but the QM Data Entry Form has ''Date Of Information'' '''2000-02-28'''.
 +
: It is not possible to Unapprove QM due to the Land has newer Date of Information.
 
   
 
   
{{NavBox Hub}}
+
Contact your [[Information Management Team | GICHD IM advisor]] if you would like to use Unapprove and the rules above should not preventing you from doing so.
  
[[Category:NoPublic]]
+
{{NavBox Technical Notes}}
 
[[Category:NAA]]
 
[[Category:NAA]]

Revision as of 16:59, 9 August 2016

Warning.jpg The Unapprove feature should NOT be used to correct or delete data because if you use Unapprove Action then all traceability and transparency are lost.

If you need to correct data, you should create a new Data Entry Form using the Update action.

If you need to delete an item, you should create a new Data Entry Form using the Delete action.

Inactive Unapprove.png

Inactive vs Active button

When the Unapprove button is inactivated then it is not possible to Unapprove that Data Entry Form. The most common reasons why it is not possible to Unapprove are:

  • there are other items linked to the item
The other items may be approved or in the workbench


  • there are other Data Entry Forms that are updating the item with later dates i.e. is not the last one in an updating chain
Example 1: an Accident was created and approved with Date of Information 2014-02-14.
Later the Accident is updated with Date of Information 2014-02-20 and with a third Data Entry Form which has Date of Information 2014-05-05.
It is not possible to Unapprove the Data Entry Form with 2014-02-20 due to it exists Data Entry Forms with newer Date of Information.


  • the Data Entry Form is linked to another Data Entry Form but Date of Information are not chronological.
Example 2: a Land was created and approved first with Date Of Information 2003-11-27.
Later a QM was created and approved with link to the Land but the QM Data Entry Form has Date Of Information 2000-02-28.
It is not possible to Unapprove QM due to the Land has newer Date of Information.

Contact your GICHD IM advisor if you would like to use Unapprove and the rules above should not preventing you from doing so.