Using the Tasking Tool in IMSMANG

129 bytes added, 18:05, 26 May 2014
no edit summary
{{TOC right}}
==Introduction==__NOEDITSECTION__
The Tasking tool allows Mine Action Programmes to perform Task planning and Task tracking capability within {{IMSMANG}}. Tasks are created by selecting objectives (Land) and then plan work items (Activities, Assistanvce, Education activities and QMs) to it. Any other related information to the item can as well be included in the Task.
Using the Tasking Tool, information operation managers can group items together for assigning mine action responsibilities to different organisations and for tracking purposes (gaining approval, conducting and monitoring).
Similar to other items, Tasks can be customised to include CDFs. Tasks, however, are somewhat different from other items in that they are entered and modified directly in {{IMSMANG}} without using Data Entry Forms or the approval process. This means that historical data about Tasks is not tracked (except for status change) and any updates made to Tasks automatically replace previous data. This provides a simplified mechanism for tracking short-term task data in addition to the traditional Data Entry Form method for other items.
{{note| The objective refers to of a Task may be a single land Land or to several lands that have the same TaskLand items.}}
<ol>
<li>Select the '''Objective''' tab in the Task Editor window.</li>
<li>Click the [[Image:FieldTemplateIcon.png | Add]] button.</li>
<li>Select a Land. Note that the Land must have status Status setin order to be possible to select.</li>
<li>Click '''Assign'''.</li>
</ol>
====Associating Creating Work Items====__NOEDITSECTION__{{note| Work Items may be created by the operation manager and are the '''planned''' Activities foreseen by the operation manager.}}
<ol>