Changes

Jump to: navigation, search

Understanding IMSMA Information Model

3 bytes added, 14:34, 9 July 2019
no edit summary
| Assistance
| Information about assistance for a person injured or affected by an accident
| ObjectProcess/ProductActivity
|-
| Education activity
| Information about an activity designed to inform or educate people (e.g. Risk Education or Victim rights)
| ObjectProcess/ProductActivity
|-
| Quality Management (QM) activity
| Information about an quality-improvement activity, such as an effort to control and monitor the clearance and/or reduction of land or activities
| ObjectProcess/ProductActivity
|-
|}
Data Entry Form #3 updates the land area's size and status after clearance operations are complete. The figure above shows how the land area's Summary is updated after all three reports are entered into the system.
{{Warning| A Data Entry Form that is changing existing information must have a Date of information that is later than the Data Entry Form that it is updating the calculation of the Summary item(s) are based on Date of Information. When the date is earlier or the '''same''', the Summary item will '''not''' be updated.}}
===Location ===__NOEDITSECTION__
The example below shows how users can build a workflow of relationships among items to model the information management process for their Mine Action Programmes. The figure shows how the Summary changes with each activity that is linked to the original Land.
# The Land starts its life-cycle as ''SHA'' with a status of Open in this example.
# When the technical survey clearance starts and the first Progress report is linked to the Land, the Land classification status should be updated to ''CHA'' and the status changed to ''Worked On''.
# Finally, after linking the Completion Report the land's status should be updated to ''Closed''.
6,632
edits

Navigation menu