Task Tab

From IMSMA Wiki
Revision as of 17:06, 7 February 2014 by Laura (talk | contribs) (Version 6.0)
Jump to: navigation, search

Tasks consist of:

  1. general information
  2. objectives
  3. planning and monitoring information that applies to the whole Task or planned activities (Work items)
  4. status history
  5. related information
  6. geospatial information.

In the Task Editor window you can see all these information organised in different tabs.

Objectives

On the Objectives tab the Task manager selects which Land should be included in the Task.

Note.jpg Land must have status set in order to be included in a Task.

Planning & monitoring information and Work item

It is not mandatory for the Task manager to fill in the planning and monitoring information metadata or to link each Work Item later to the reconciled and approved object that is the outcome of the Task.

Related information

On the Related information tab the Task manager may link to the Task other objects that are either helpful for his own planning or for the planning and/or execution of the Work item for the executing organisation. On this tab all types of objects are possible to link including Ordnance and other Tasks. Note that this is only for information purposes and is not intended to be subtasks of Task.

Geospatial information

In the General information section you link the Task to the Country structure which makes also the Task to interact with the Country Structure Pane. On the Geospatial tab it is possible to plot the geographical extent of the Task.

Note.jpg In version 6.0 no fields have been added and the Statistics tab has been replaced by a printing functionality .