Changes

Jump to: navigation, search

Understanding IMSMA Workflows and Business Rules

5 bytes removed, 22:09, 1 May 2013
no edit summary
Once the land/activity relationships and workflow are defined and documented for each type of land, the next step is to define how progress data for the land clearance processes is collected. Traditionally, incremental progress data is collected using progress reports. These reports are typically linked to the overall clearance operation and are used to collect the incremental progress for a reporting period, usually, the number of mines/UXO cleared, area cleared and hours worked. In IMSMA<sup>NG</sup>, each progress report is stored as a new activity and linked to the clearance. As a result, individual progress reports can be queried to determine how much progress was made during a given reporting period. In addition, aggregate progress information can be queried for each clearance (for example, the total mines that have been reported cleared for a given clearance operation).
An alternative approach to storing progress information is to collect incremental progress reports and reconcile them as updates to the clearance using the combine option during reconciliation. Using this method, progress reports do not create independent activity items; rather, their information is combined with, and added to, the clearance information collected to that point. This approach simplifies the reconciliation step for progress reports as well as provides a simple summary of clearance data on each land in the current viewSummary. It may, however, become slightly more complicated to determine progress during individual reporting periods. Information managers should assess which approach better meets the needs of their programs when selecting an approach to tracking progress.
In the example below, progress reports were collected for three separate reporting periods during a clearance operation. Collecting and linking information in this way makes it easy to determine that in Period 2 (PR-2), 4,500 sqm were cleared and 25 AP mines were found and that, overall, 15,000 sqm were cleared and 61 AP mines were found. A defined, standardized approach to collecting and storing progress information simplifies querying and reporting of statistical information and is a critical element to supporting operational mine action information management needs.
2,186
edits

Navigation menu